A38 Roundabout Progress
Phase 1B
Restoration

A38 Roundabout Progress
by: Will F.
The Contractors Griffiths restarted work in early April keeping to Covid 19 guidelines and have completed the BT duct bridge.
More info on Gloucestershire County Council Web site. There is also some earlier drone footage available on the site.

The north wing walls for the canal to eventually go through now completed.

Now digging a big hole in the middle of the roundabout for the canal with a huge pile of spoil being transported by a fleet of lorries to shore up the bank (I think) at Northleach where a road is closed due to ground slippage.

More good news is the swans are still in residence near Occupation Bridge!