Blunder Lock refurbishment

Phase 1B
Restoration

Blunder Lock refurbishment early jobs

by: Andy P.

Jon P crew had made a start on building the scaffolding inside the lock, so we arrived to finish this off using our recent training as scaffold erectors. Mind you, to see grown adults of certain vintages, putting on the new harnesses was something to behold. We tried inside out, upside down, back to front, reading the instructions, until, some considerable time later; we descended the depths of the very smelly lock. Waders were also the choice of outdoor wear and Jon and Bob waded through the ancient muds to fix the scaffold feet. All the poles and fixings were lowered down and gradually the structure took shape.

The bottom cill had been damaged and looked worse for wear. So, we thought it would be an easy task to lift it out with maybe some encouragement and bashing in key places. Not a chance. The stop plank channels were cut out and extended so the new metal ones would fit the current range of stop planks.

Jon hired in specialist contractors to cut out the 2 ladder recesses. A neat job with lots of very heavy stone to get out of the canal

 The Godwin pump decided it was not going to play any more. The lock was filling up, which would have compromised the lower dam. So a hired pump was brought to site and coupled up, but just wouldn’t start to pump water. Much head scratching, phone calls and button pressing ensued. A quick wriggle of the inlet pipe and a reseal and off it went-simple. The dam people were called back to make sure all was well-it was, which was a major relief.

Latest News