Blunder Lock – the end maybe?

Phase 1B
Restoration

Blunder Lock – the end maybe?

by: Andy P.

A lot more cutting and drilling and chiselling was needed and it went on for a very long time. Some very sore hands and arms were the result. The holes had to be cut so as to form a platform for the brick repairs. The repairs may look a bit stark but when the lock refills it does not take long for them to get covered over.

 Before and after looking towards the towpath side

Repairs on the opposite side

Middle of the lock towpath side

Jon’s crew had taken a large portion of the scaffold down and when the repairs were completed the remaining scaffolding was taken down and transferred to Prentice field ready for a trip to Newtown lock. The old tool store was moved, ready for its contents to be transferred to our new to us and bigger tool store-nicely fitted out by the depot chippies. The groundhog will be moved next so that the smokey genie can be fixed hopefully.

The job has been completed in less than 3 months through a joint effort by 2 brilliant crews working together. An excellent job all round and a big thank you to everyone. Some lessons have been learned and can be used at our next stop at Newtown lock, for basically a similar exercise.

At some point in the future new top gates and paddle gear will be bought and fitted but not this month.