Delilah Springs a Leak

Maintenance

Delilah Springs a Leak

by: Steve P.

The barge Delilah has been upgraded over the last year to have an engine and hydraulic system that drives both the propulsion unit and a crane arm so that it can be used for lifting and moving operations.  After the upgrade and testing was complete Delilah was moved to Ocean Meadows just west of the Ocean Jubilee Bridge to do trials on emptying hoppers into the newly cleared Ocean Meadows site.

The boat team came in on Monday, after the recent heavy rain, to find Delilah sitting on the bottom with several feet of water in the hull covering the batteries and lower part of the engine, which then explained why the bilge pumps hadn’t kept her afloat.  After pumping her out (again!) the boat team discovered that it wasn’t just the heavy rain that had caused the issue but a number of hosepipe sized leaks along the waterline at the bow that had overwhelmed the pumps.  Further investigation showed that there were not 2 but 4 or more leaks, and that the only solution was to weld new plate over the rusted areas.

The previous week the dry dredging team had helped the boat team to pull Annette up the mud “slipway” at Harpers Field so that welding work could be done on the outboard motor mountings, but Delilah’s need was greater so Annette was re-floated and we awaited the arrival of Delilah.

By the time that she arrived Harpers Field was full of boats and people with Boatmobility as well as Annette, Delilah, Goliath, a full mud hopper and then Wookey Hole all there at the same time, but eventually Delilah was lined up with the slipway, and Vince with the 13T digger readied to pull her out.

This had been done before, but with a dry slipway and less weight in Delilah as this was when she was an empty hull, and it soon became apparent that the task was at the limit of the 13T digger’s capabilities.  We tried smoothing the ramp, putting in what we hoped were slippier bog mats for her to slide on but all to no avail, at which point it was time for a late lunch and rethink!

After lunch we brought in the Frank with the 9T digger as well, and after cleaning up the ramp and bog mats the task restarted.  We eventually got the front of Delilah out of the water onto the bog mats but it was clear that she wasn’t going to move any further, and that whoever was going to do the welding was going to have to do it while working in the mud under the bow!

All that was left was for Frank with the 9T digger to try to clean up what had once been a nicely graded slipway into something less like a ploughed field.

Hopefully when we get back next week Delilah will still be wedged where we left her and the stern won’t have sunk due to similar leaks and the team can start to work on her again.  Meanwhile Chris is off to find some more batteries and the engine will need draining and filling with yet more new engine oil before we can get back to the planned dredging activities!

Latest News