Dudbridge Lower Lock

Maintenance

Dudbridge Lower Lock – May 2020

by: Andy P.

Well it has been a while and the wall has not really improved with age. The stone has dried out in places but is still pretty rotten.

The plan was to cut out shelves and cut back the stone to something more solid, so that new brickwork could be laid to fill the gaps. Hammer and hand chisels were used until mechanical devices were bought and borrowed.

Then the bricks arrived. However access on the building side of the canal was not available-don’t ask. The new Lidl store area was being boarded up so we hurriedly hand carried and stacked 2000 bricks. Ah yes but now need to get them to the other side of the lock-a job for later.

Next job was to collect virtually all the scaffolding to be used to cover both sides of the lock as the other wall needs some attention.

Ever resourceful, the old bricks were cleaned and are being reused where possible. Imperial v metric will be managed, with no problem.

Careful measurement essential to fill the gaps and whilst still digging out the poor stone.

Great joy and celebration as the first bricks are laid-progress at last

Lots of wall ties are being used to tie in the brickwork to the stone behind. We are using plenty to make sure and inserting where we find solid stone

Working 3 days a week including bank holidays to try and catch up before the winter frosts! It has been very hot in the lock some days but worth it to make progress. Most of the usual suspects have been involved. Bob A, Mathew, Duncan, Bob K, Jon P and Andy P