Dudbridge Lower Lock

Maintenance

Dudbridge Lower Lock 20th Jan.

Dudbridge Jan 20th 2020

An earlier trial indicated that the big pump dropped the lock by 2 stop plank handles in 1.5 hours. Therefore 8 planks to the bottom would be done in 6 hours. Therefore, the pump was turned on at 7am to give us time to work on sealing any leaks whist still in daylight.

As the water went down the previous low leaks were now much bigger leaks-not a good sign. The usual gang of folks were joined by Jon P who helped with constructing and lowering a sheet to try to seal the gates. It did not work as too much water had been taken out. We spend a lot of time watching the water levels reduce and getting very cold-a bit like watching paint dry.

Patricia and her crew were called in to try and push the planks down to help seal the leaks. This also did not really help.

The levels were going down really slowly. Another king post arrived and a plan hatched to install it, along with the supporting wires. Aquila was brought back and holes drilled and adjusters fixed so that the post at least fitted over the now 9 planks.

A shiny new sheet of plastic was cut and lowered behind the planks with the hope of sealing the leaks. Innumerable sandbags were lowered on top of the submerged sheet which did reduce the flow a little.

By now it was getting dark and we left just as the 8th plank came into view. So near yet so far

Tuesday update-the lock is empty and gangs of folks are erecting scaffolding. Andrew R and Patricia crew are sealing the final leaks from the planks.

I am sure Jon P and Andrew will add to the story.