Dudbridge Sluice Log removal
Maintenance
Dudbridge Sluice Log removal
by: Chris K.
A return investigation was required to have a look as to why the offside sluice had still not returned to full flow at Dudbridge lower lock after removing a log two weeks ago. Looking into the sluice with torches revealed that the blockage was a large wooden obstruction.

The first job was to drill a hole into the log so the long auger bar could be screwed in. Once secured we were not able to pull out the obstruction by hand, so it was decided to use the near side lock gate as a lever.


A very large piece of timber that looked like part of a lock gate appeared. The question everyone wanted to know is “where did it come from”? The offside sluice is now fully operational.