Dudbridge Wharf repairs
Dudbridge Wharf repairs
by: Andy P.
Several smallish jobs have been completed over the last few weeks.
Some finishing touches were added to the groundhog welfare unit by purchasing essential items such as washing up liquid, bowl, coffee, pens and most important of all, some biscuits. It is now filled with diesel and ready to go when the stop planks finally stop water and the scaffolding inside Dudbridge lock is built. The wall repairs can then commence. Waiting patiently.
Further down the towpath there were 2 loose coping stones that needed fixing. Seemed a simple enough job-but we should know better than this by now. We needed to work from a boat that was gratefully supplied with Myron, Dave and Jasper. We gently dug around the 2 very large stones. After a few minutes and a lot of hands and heaves, one stone was lifted onto the towpath as it was about to fall into the canal.
With a bit of digging the problem became obvious. A large tree root and attendant soil was no longer providing any support. Bob, on trusty disc cutter, trimmed the largest stone back and the bits were used to rebuild the wall. In fact a lot of bits were needed to back fill and rebuild the wall. Another stone had to be supported as the tree roots were the only thing holding the stone in place. We finished just before dark as Jasper purred away into the sunset.


I am sure we will have to return as the rest of the wall is not in the best shape.