End of Concreting at Western Depot?

End of Concreting at Western Depot?
by: Steve P.
The last major task for the WD update is to relay the yard area in front of the containers, with drainage for any rainwater or spillage into the separator tank between the machine shop and the barn.
After a lot of measuring, it was decided to use a drainage gulley with pipe into the separator, but the levels proved difficult especially with the drainage pipe which had to pass over or under 2 electrical conduits.

By close of play the trenches had been completed and the drainage duct places loosely in position with some concrete to hold it all in place, so the following week saw a lot of concrete mixing underway to build up the yard side of the gulley to what will be the finished yard level. By the end of the day the full length of the gulley had been concreted in, and a watering can test done to prove to Reg that it did drain ok!

Attention then turned to the area in front of the barn which needed more shuttering and concrete to get a 2nd solid edge to the new yard area, with some running adjustments as the electrical conduit was again unearthed! Another hard day saw the concrete completed with the diesel cement mixer put into service alongside the trusty electrical one.

The mini digger continued to excavate the yard area to get the required 200mm depth for the dry concrete mix to be used for the new surface, but at least we could now start to make sense of the levels and drainage! The end of a long day saw this area completed, and work starting on the area between the drainage duct and the containers.

Work then continued with yet more concreting, starting with the area between the containers and the new drainage duct. Fortunately, Chris and Colin weren’t in so at Martin’s suggestion we closed and locked the containers before laying the concrete, but this did cause some confusion when someone wanted a tool or materials from them! By Monday afternoon last week even Reg was feeling sorry for us and took a turn at mixing and delivering the concrete! By the end of the day, we had run out of cement and aggregate again, so Martin, after some complaining, agreed to order more!

Monday this week saw the area in front of the containers completed in record time with a larger team, and work started on the final area in front of the chippie’s shop. Alun helped us to extend the threshold so that we could get the levels right and tamp the concrete in to place, with access to the chippie’s shop by either walking a plank or edging round the wet concrete! So far we have only found 1 footprint in the wet concrete, but more may still come to light!

This hopefully completes the concreting for the yard (to the relief of all the team!), so we can now finalise the levels ready for the yard surface material to be delivered, spread and rolled, hopefully with all the surface water now directed towards the duct and drain.

It looks as if the resurfacing will have to wait until the New Year, and will need a full team effort to lay around 70 tons of material in 2 layers of 100mm with significant rolling and compacting to get a hard and resilient surface. Reg is now considering whether to just hire a roller, or get an experienced man and a roller, which will probably get a flatter surface finish than we could achieve!