First Run Through…
First Run Through….
by: Buffs
First Run Through for the Official Opening of the Ocean Rail Bridge
On the 23rd of May 2022 we will be celebrating the formal opening of the new Ocean Railway Bridge. There will be a sail past of a flotilla of CCT workboats, community and pleasure craft. Timing will be an essential part of the event as the boats pass through the swing bridge and on through the new bridge after the ribbon is cut by the VIP.
To achieve this feat of close quarter boating a run through of the flotilla movements was deemed necessary. Communication between the boats and boats and boats and the swing bridge was also to be tested. This seemingly simple event took place on Wednesday. Anyone who has had to marshal different types of mobile objects through a small gap in procession will not be surprised at the way the morning unfolded.
The swinging team, which included WD manager Reg who is co-ordinating the movements, went to meet the flotilla at the assembly point, nominally Boakes Drive landing stage. Following the towpath from the Ocean towards Nutshell Bridge the flotilla hove into view just above the bridge. Collecting the boats together a short briefing session led by Reg went through the plan of the morning. Radio protocols were established; formality above familiarity is the order of the day. The order of procession finally agreed and the turning places agreed. A close order of progress was to be the target for the day.
The swinging team returned to the bridge accompanied by Jasper in the hands of the Captain of Boats, Chris K. Jasper was substituting for Zephyrus, aka the Wheely boat operated by BoatMobility, which will conduct the Ribbon Cutting party from St Cyr’s landing stage to the ribbon.

With Reg standing on the bridge and Chris and Ian ready at the winder the go was given. The chains were pulled across the roadway showing that the bridge was to be swung, Jasper eased off the landing stage and the 170 turns on the handle were started. As Jasper approached the bridge the flotilla was still beyond the bend. The bridge pivoted as the jacks withdrew and the swing started. But where was the flotilla. Through the willows the first boat appeared at the bend, a little later than anticipated.

The bridge swing continued with Ian and Chris getting more practised in the smooth handover of the winch handle so that no effort was wasted getting the handle moving again. After Jasper the procession was Margaret, Patricia, Perseverance and the Augustus Gloop/ Annette II combination. The separation was not ideal. Augustus Gloop used all the width of the bridge pass to get through. Gloop has no more than 15cm/ 6” clearance here. John, standing on the port sponson was giving hand signals to the helmsman 40 feet away.

With all the boats through the bridge and moored the other side of the new bridge Reg led a learning from experience session. Timing, separation and signalling were discussed. Joined by the event organiser Aimee the discussion was broadened. Lunch and tea and biscuits for crews and marshals was one topic, dress codes were another. Washing machines at home will see extra duty over the next week. The role and positioning of the Media was also discussed.
Crew dispersed to their boats and started to reform their line whilst Patricia was turned in the wider and deeper water on the west side of the rail bridge. The bridge was swung for the flotilla to return eastwards. One benefit from the outward passage was that helms now knew the separation required and processed in a much closer order on the way home. Gloop will have a second hand on the sponsons to help navigate through the swing bridge pass.
Dredging and towpath restoration will continue and Delilah will be taken East soon. Investigation of the leak will continue with some drastic measures being considered. More on this later on the CCT website and this Blog.