Harper’s Field
Harpers’s Field
by: Dave C.
With still no big hammer, the Harper’s Field Team set about removing the main hydraulic ram from Weedy so Arthur could work on it. It will only take 10 mins they said, how many times have we heard this only to find out it takes 3 hours! It started with Vince, Jeff and Steve L removing the propeller so we could get at the bit we wanted. Off it came with a hitch and we all thought 10 mins might be realistic, until we tried to move the ram.

Having got all the hoses off with only a little resistance (by now we were way past the 10 min mark), a unanimous conclusion was reached, this is going to be heavy. So we call for the big digger and Andy J and Les M joined in the fun.

With the big digger taking the load, it was just a simple case of slipping the ram off to one side so it came free; the ram had different ideas and refused to budge. Step one in all CCT construction is to hit it with a hammer, so Jeff repeatedly tried to pursued some sort of movement, unsuccessfully. Step 2 is usually apply WD40 to the offending bit of metal, this gave some hope, and with repeated Steps 1 and 2 movement was achieved. until with a big cheer the ram moved clear, held up off the floor with the big digger.