Harpers Field Gets an Upgraded Silt Offloading Deck

Maintenance

Harpers Field Gets an Upgraded Silt Offloading Deck

by: Steve P.

We have been using Harpers Field for silt offloading since 2019, and with nearly 500 hoppers and 7000 cubic metres of silt unloaded the off-loading dock was looking rather the worse for wear.  In spite of previous attempts to strengthen what had been intended as a “domestic” landing stage the deck area was becoming unsafe, and was taken out of service while alternatives were found.

A number of schemes were proposed, but with no budget these were really temporary solutions based on strengthening the current deck using what materials were around us, until a visit by David from the landing stages team resulted in a decision to remove the old stage with its plastic wood support legs, and effectively dredge to bank.  The team then found some 30 steel piles stored at Prentice Field which happened to be just right to build a 14m long piled landing stage, so a new plan was born!

The first step was to dredge the area between the old landing stage and some trees after a trial showed that the 13T digger had enough reach to empty barges at this point while the upgraded landing stage was designed and implemented.

With the old decking removed the original structure could be seen, and the 13T digger made short work of pulling this out onto the bank, although it took rather longer to unbolt all the steel parts so that some of this could be re-used. 

The area adjacent to the dock was scraped clean and level ready for the new dock, with 3 of the 4 original concrete support pads being kept as a good foundation for the dock (it would have been 4 until Harry decided to move the 4th and only part way through realised how big it was!)

Samson had been moored near Harpers Field Auctions, so was moved to site, and the outriggers and piling guide fitted ready for the piling work to start with the steel piles being moved to site by both manpower and a 13T digger (much easier!)

Piling was soon well underway working from the Ryeford Bridge end, but some piles proved difficult to drive to full depth.  The team persevered and by the end only 2 piles needed to be cut to length!

With the main piles in place the next job was to drive in some “king piles“ further into the field which would then be linked to the front piles by rebar tie-rods to strengthen the dock area.  The original plan had been to have 12 ties, but the final total ended up as 19!

Even though there was no budget for the dock work Reg agreed to buy the rebar material to make the tie-rods, and Chris and Jeff at Western Depot were persuaded to weld these to size after which the dry dredging and landing stage teams worked together to install them.

With the main structure completed the dry dredging team moved hardcore and type 1 material down to the dock which was firmed and levelled using the 13T digger when this wasn’t in use for hopper unloading (which continued all the way through the dock upgrading process!).  With the hardcore in place all that was left to do was to fix the mooring bollards, and we had a new dock!

Within minutes the first full hopper arrived, and with the new dock and the temporary offload area we now have space to moor or even unload 2 hoppers at once!

The lower height of the new dock with its stronger construction provided a much better base for the excavator to work from with better sight lines into the hopper and less trip hazards on the dock, so a better and safer solution overall.

All that now remains is to install some fenders and tyres to prevent damage to the mud hoppers and dock itself and we have a solution that at minimal cost should allow better and safer silt offloading for many years to come.

My thanks to all who have been involved in this which has been a great example of cooperation between many different CCT groups all working together to improve the canal and its environment.