Harper’s Field update
Harper’s Field update
by: Dave C.
The big news from Harper’s Field on Monday was the Big Digger was working again following the replacement of the push-rods; there were in fact 4 separate faults on the machine and credit goes to Joe Blackwell for his diagnostic and engineering skills. First order of the day was to try the refurbished piling hammer on the piles that had refused to move. Unfortunately the piles won again, and we all simultaneously reached the same conclusion, ‘get a bigger hammer’.
With the (lack of) piling done for the day, the team turned its attention to assisting the Boat Team. First up was the repositioning of the hydraulic arm that had been placed in such a way it could not be used. With Andy J, Les M, Jason and Kay all looking into the whole a cunning plan was devised that minimised the movement required. With Ron K on the Big Digger slow and gentle persuasions were made until the correct position was achieved.

Next came the Weedy. Again much discussion took place and it was decided to use the interim slipway Bob A had made some, months ago and one of the bog mats that had been conveniently stored in the Field. Again the Ron on the digger, slow and careful movements were made with some pushing and shoving, and ensuring that the prop never touched the ground, Weedy was secured on dry land ready to be worked on.

While all this was going on Les P was in the welfare unit planning and then installing the internal electrics. With just the plumbing to do, the Welfare Facility will be up and running before the cold weather sets in.