Inglesham Spillway Update Autumn 2024

Phase 2
Restoration

Inglesham Spillway Update Autumn 2024

by: Neil D.

Over the Summer the Thursday evening team have been mainly concentrating on rebuilding the Spillway adjacent to Inglesham Lock but, with several excursions in support of the Weymoor Bridge culvert project. The Spillway is unusually large for a Lock Bywash. These usually take the normal flow of water in the Canal around the Lock via a culvert and feed the section (Pound) below. However, as Inglesham Lock is the last one on the Canal there was no need for this and it discharged into the nearby River Coln via a short open ditch. It would appear the Canals builders took advantage of this and used the spillway to also take surplus flood water as well as the normal flow out of the Inglesham Pound. This would explain its large size.

The Weir crest being prepared for rebuilding

The first task before restoration could begin was to remove the top layer of clay puddling on the Canal side of the Weir crest and to remove all the loose masonry on the crest itself. Without wanting to completely dismantle the structure, it was taken down to a level suitable for a new foundation. There were several places where previous repairs had been made and these required some imaginative brickwork to bring back level and tie-in to the new build! Most of the Dry Stone walling on the Canal side of the Weir crest had already been rebuilt along with the Lock some years ago but, a small area at the top of the photo above had not. This was the next part to receive attention.

The missing section of Dry Stone wall reinstated

Next, the first part of the side wall of the Apron below the crest was extended from this Dry Stone section but, now using Lime Mortar. Originally these side walls were also Dry Stone but, had not held up well against the flow of water. Over the last couple of months, the Weir crest itself has been rebuilt in Brick up to the established water level, creeping forward a couple of feet each week in the limited time available.

The new Weir crest begins to take shape

With the night’s drawing in and the clocks about to go back, we received a significant boost by a visit from Watery Recovery Groups BITM team. They were on site for a weekend and on the Saturday, we were blessed with good weather enabling us to almost complete the Weir Crest including replacement of two of the Coping stones at one end. These are actually above water level & extended 4 feet or so in at each end. We think these were added at a later date to channel the water flow away from the sides of the Apron below, probably to avoid erosion of the original Dry Stone side walls. A start was also made on the opposite side wall of the Apron but, unfortunately the heavens opened on the Sunday so any further construction work was ruled out and the team concentrated on vegetation management tasks. A big thanks to WRG BITM for this boost that inspired our regulars on the last Thursday work party this year, to finish off the Weir crest with the remaining coping stones. We will continue the restoration next spring when we will finish the side walls and replace the missing stone work on the bed of the Apron (commonly referred to as the ‘Riff Raff’). Much of the loose stone work having been removed over the weekend. The final task will be to pack behind the Dry Stone walling with puddle clay and replace the puddle clay layer removed from in front of the Weir Crest to ensure there is no seepage through the structure.

WRG ‘BITM’ Team at work on the Spillway  (the lock and Canal are off to the right)