Missing Mile Update: 120 Metres Complete and Counting

By Andy T.
Approximately 120M of canal has now been dug, the bottom levelled and the banks either side shaped and compacted. Only another 630M to go on this side of the motorway!!

The first phase of the missing mile crosses a floodplain. As you can imagine there are significant long term environmental risks that need to be taken into consideration, thankfully that task fell upon Rob and his team of design engineers.
To comply with environment agency requirements the banks must be a specific height above sea level, be constructed with the outer banks at an agreed profile ensuring that the ability of the floodplain to function correctly at times of flooding is not compromised.
As well as complying to environmental requirements consideration is being given to the users of the towpath. Once compete the towpath will be on the south side bank. The top of the bank is being constructed to a minimum width of 2.5M providing a wheelchair friendly towpath.
The team are constantly checking the depth of the dig, the width of the cut and the height of the banks. At times it may seem there is a volunteer just wandering around with either a measuring stick with a laser level or a GPS mapping tool, rest assured they are not. This is probably the most critical role in the team ensuring we stay on track, comply with the environment agency requirements and maintain the canal depth.

The banks are being constructed from subsoil. This is compacted in layers that are approximately 300mm thick using a 4T ride on roller, definitely not a machine to use if you suffer from a bad back!! Once the layer is compacted more soil is added and the process repeated until we reach the required height.

The steeper slopes are compacted using a remote-control sheep’s foot roller, the roller is controlled by the operator using either a cable or a wireless connection.

Once finished the banks will be dressed with topsoil, from Mount Oldbury – see previous post) and seeded.
On the canal side of the constructed bank a layer of approx. 900mm of clay will be used to dress the bank ensuring the canal remains watertight. Respect must go out to the original teams that built the canals for the physical effort required not just for digging the channel but puddling the clay and removing the waste material.
The team are now focussing on lining the first pound, as well as digging the second pound and completing several trial digs for clay and to assess the ground conditions.