One Sunday evening we had a second and this time successful break in. Locks cut off and about £1000 of kit taken from the tool store. They even tried to get into the cabin to steal the biscuits.

When cutting out the ladder recesses it creates a lot of rubble. We are always grateful to Chris F and Steve V and crew for readily bringing things and taking things away

After a ladder recess is cut out, the chippies have to make shuttering to fit in the gap. Concrete is then poured behind the shuttering. Shuttering is removed, often with difficulty and the process repeated several times.



The next big and novel job was to fill the brick rubble voids. After a lot of searching (thanks to Will F) and discussions with Rob B, a particular specialist grout was sourced. This needed a pump (expensive) to be hired and delivered. After a failed first attempt, where the material set in the pump and hoses, we managed to get the first batch into a hole in the wall



The product should mix into a smooth paste and not like 1 batch we had, which was the wrong spec and out of date.

Over the following 3 weeks we used 90 bags of grout and injected it into the walls, about 1000 litres of product. Holes were drilled at spaced intervals both high and low. Sometimes many batches of grout went in a hole and others nothing. Some of the holes leaked clear water for many days.
Numerous air bricks were found and cut out, to be replaced with new brick work.

Holes were drilled into the ladder recesses as well, but no grout penetrated the walls.

We also found a date marker from 2014 but that does not seem to tie in with anything.

The end lock wall was also patched up as there was a lot of broken concrete and brickwork.