Ocean Bridge Electrification

By Steve P.
When the Ocean swing bridge was installed in 2012 it was manually operated, but it was little used as the navigable canal ended at the Ocean. Since the Ocean Jubilee Railway bridge was completed CCT have been dredging from the Ocean to Bonds Mill, and as since the Bailey bridge was installed this has been extended beyond Bonds Mill. This has led to increased use of the Ocean Swing Bridge, and dredging from Ocean to Pike Lock could mean up to 300 mud hopper loads passing through the bridge.

The bridge is hydraulically operated with rams that raise and lower and then rotate the bridge, but it takes nearly 200 turns of the windlass to fully open and close! This has been a major problem form the tug crews, and has led to some short-term initiatives to try to reduce the workload, but SVCC and CCT have now agree to change the bridge to electrical operation.

The project, and its budget, have been approved by the Delivery Board, and involves a number of elements which are now underway:
- A new mains supply from an adjacent power pole to a control cabinet on the south (towpath) side which boaters will use to operate the bridge; the controls have to be on this side for single-handed boater operation.
- A cable bridge to carry power and control cables across the canal; various options were considered, but the cable bridge is the cleanest and safest option although steps will be taken to make it visually attractive and vandal proof.
- The hydraulic power pack and controls will be in a cabinet on the north side so that they can be connected into the existing pipework, and hydraulic power does not have to be taken across the canal. It is hoped to be able to open and close the bridge in about 60 seconds, and provision will be made to control the hours during which the bridge can be operated.

It is hoped to complete this work by the end of 2025; foundations have been laid for the south and north bank control cabinets, and the south cabinet is almost complete with a steel door and frame fabricated at Western Depot. The cable bridge will also be fabricated at Western Depot, along with the electrical controls, but the hydraulic power pack will be bought in from a local specialist.
Information signs are at the Ocean Bridge site, providing an overview of the works taking place: