Oldbury Brook Update

By Andy T.
Over the last few months significant progress has been made at Oldbury Brook from the CCT team!
Oldbury brook has been lowered and now runs through three 600mm pipes for a length of 42 metres, under what will be the canal base and the edge of John Robinson lock.
On the downstream side of the pipes, the banks have been reinforced with rocks, known in the trade as Rip Rap stone, and concrete to reduce the impact of erosion from the outflow. Further downstream Oldbury brook has been cleared of several fallen trees and split willows that would potentially impact the flow and cause water levels upstream to rise.
Recent bad weather has highlighted the urgent need for a trash catcher to be built and installed over the inlet to the three pipes. This is due to the surprising amount of rubbish and debris coming down Oldbury brook.
The pipes were covered in stone and then a concrete protection layer was poured over the entire length to prevent potential damage from overly keen dredging activities.

Once the concrete base was laid a new bund was built upstream of Meadow mill spill weir with a bypass pipe installed to ensure the working area could be kept as dry as possible.

The bund was created using the now tried and tested method of lowering filled dumpy builders bags in two lines and then backfilling the middle with stone. This approach provides two distinct advantages, it significantly reduces the amount of material used to build the bund as well as providing a stable base for excavators and dumpers.
Once the bund was in place and the bypass pipe installed, we began the task of moving the silt. In places the silt was over 4 feet thick as tested by one of the team who bravely donned a pair of waders and went for a walk in it.
The silt was moved by using three excavators and two dumper trucks. Two of the excavators moved the silt towards the third which loaded the sloppy stinky goo into the dumper trucks.

Comments were passed by several walkers and passers-by that at times it looked like a ballet of excavators as the machines moved in perfect unison. We estimate that over the period of removal we made in the region of 150 dumper trips.
The silt has been stored in a nearby field to enable it to be dried before being moved to backfill the holes where the clay has come from.
Whilst the CCT volunteers moved the silt, contractors brought to site approximately 80 lorries of blue clay, this is being used to reline the canal and rebuild some of the banks. Is this enough clay? We are not sure. The banks were built in the 1960s and 1970s when the east end of Westfield lock, now John Robinson lock, were destroyed. These banks are made of an interesting mix of stones, soil and rubbish. We have had to dig them right out in places and will rebuild them using either Legato blocks, backfilled with puddled clay or where we have sufficient space, we will create the banks at the correct angles directly from clay.
The latest activity has seen the team focussing on re-lining the base of the canal with approximately 400mm thick layer of clay to ensure it is waterproof and keying-in the new bank area to ensure a good seal between the old and new clay.

The team has developed a high level of respect for the original builders of the canal, as using modern machinery we have struggled at times to make good progress. We quickly realised how much manual effort was involved in laying the original clay liner. We dug a number of test holes to discover the original liner was over 1.2m thick, they did this with donkeys and people that were allegedly powered by cheap local beer!!
Doing this work we have learnt several lessons which we will now take forward into constructing the Missing Mile. It has become increasingly evident that the fleet of machinery used needs to be reliable, fit for purpose and appropriately sized to ensure speedy progress.