Pat’s Progress II

by: Peter A.
With a pause in the dredging of the Bonds Mill to Newtown Lock section, we have used the time to set about tackling the restoration of Patricia…….again!

Back in 2018 the story of the restoration of Pat was recorded on this Blog under the heading of ‘Pat’s Progress’. Hence the latest heading. She has been on the slipway at Ryeford awaiting attention, still loaded with all the debris and detritus resulting from her sinking at the Ocean Railway Bridge.
Tuesday was spent clearing out each of the cabins, removing epic amounts of filthy debris, with our intention to get the all surfaces prepared for pressure washing. This we achieved.

Also, to facilitate this process we have moved our floating facilities unit ‘Bob’ to the rear of Pat. Bob has a large useful generator in his arsenal. Before pressure washing and bilge cleaning can begin, the engine needed to come out. Wednesday was usefully spent getting equipment to site and also disconnecting the engine and undertaking the lift.

It has now gone back to the depot to have the suspected bent con’ rod replaced, together with a thorough clean and inspection. We recorded all the connections prior to disconnection.
Although Pat did not sink because of her stability, she has always been a bit ‘tender’ in the water. The difference between her and Hamster is remarkable. We are considering modifying the cabins to remove a lot of weight that sits above the water line. There is some 670kg in the cabin metal over the engine and facilities area. If that can be moved to the bottom of the bilge, it will make a big difference to her.
On a more serious issue. When Pat sank, we believed that only two persons were on board and they exited the boat quickly. However, there was a third! ‘Dredger Derek’ was found, still in the operators cabin, looking seriously the worst for his experience. He has now been returned to his creator for a major act of resuscitation. You’ll be kept fully informed of his recovery.