Pike Lock 4th May

Pike Lock 4th May
by: Matthew J.
Mud, Glorious Mud
Following the successful removal of the stop planks, the next job was to remove the mountain of mud and silt that had accumulated behind them over the past 20 years or so in order to provide clear access to the stop plank sill and wing walls. We had already established that the mini-digger was not capable of reaching all the way to the bottom, so the only option was to hand-dig the silt into the digger bucket and transfer it to a hired-in dumper at the side of the lock. With Duncan on the digger, Vince on the dumper and a small army of mud-wallahs assembled in the lock, we set to work.


We had to be careful not to remove too much so as not to destabilise the aquadam above it, but by the end of the day the job was done and the previous cliff-face of mud had been graded back and replaced by a line of sandbags to direct the flow of water into the culverts.