Piling begins above Bagpath Bridge

Maintenance
Restoration

Piling begins above Bagpath Bridge

by: David M

Piling begins above Bagpath Bridge

Dredging our way up to Stroud Brewery took its toll on our kit, and the last couple of weeks have been spent repairing the crane, with hydraulic fittings repositioned and the boom ram restored to former glory. It is now as good as new, and should remain so using more conservative operating limits.

We have made a substantial steel piling frame, which allows sheet piles to be placed accurately in all dimensions (pitch near-vertical, yaw vertical, and roll not at all except to follow the towpath edge.) The design allows us to position the start end of the frame on the last-but-one completed pile, our barge outrigger holding the other end. About 11 of these piles can be pushed in at a go, in two stages, first with the frame in place, and then without.

Minor adjustments were completed with angle grinder and welding kit. Once the process was established we moved at a good pace, and can probably avoid stacking piles on the towpath as we continue, picking them out of the hold as required.

It’s not every day that long-made plans work exactly as intended, but today they did.