Project Dredgersaurus – With inTent

Maintenance
Phase 1B

Project Dredgersaurus – With inTent

by: Peter A.

One of the issues that cause us delays in getting started in the morning is the inevitable presence of condensation on boat components stored outside.

To help mitigate this, we have deployed an old donated tent to cover one of the fibreglass cabins stored out in the yard. So, if the odd shower should also come along, then work does not have to cease either.

Our attention has been directed towards getting the fibreglass painted and installing the numerous number of fixtures and fittings which belong on the structures, such as air vents, bits to support the window shields and the new metal hatch covers.

In the workshop, good progress has been made with the front leg access walkways which are used to set the leg stabilisers when the boat is deploying its spud legs. By the end of today, both were mechanically complete and one sported the first coat of paint. We will soon be affixing them onto the boat.

More good news came in the form of an image of the completed clam shell bucket and rotator on a pallet ready for dispatch. We may well receive that next week. Hydraulic plumbing can commence once it is affixed to the JCB boom.

( I bet they cut the grass before taking that photo! Although the hedge could do with a trim)

Plans have been drawn up for the new exhaust assembly on the engine. We need to procure the parts and assemble the kit of bits, then it will be possible to fire up the engine and get the hydraulics working to help commission the new clam shell bucket. However, there’s the small issue of electrics to install as well.