Towpath Re-opened at Griffin Mill
Phase 1A

A report from Ken BaileyStroud’s towpath walkers will be delighted to hear that Cotswold Canals Trust volunteers reopened the towpath at Griffin Mill Lock on Saturday 17th December. OS Ref: SO 858036 | |
Eight volunteers erected forty Herras fence panels from the lower bund to the top bund and round the spill weir. Many wheel-barrow loads of crushed stone & rubble, recovered from various parts of the site, were then placed to form a reasonable towpath surface through the mud. A number of drainage channels were also cut to allow the site to dry out. A section of the concrete block dam, constructed across the head of the lock in the mid-1970s, was removed in readiness for volunteers to commence work early in the New Year. | ![]() |