Tug Project – Wk4

Maintenance

Tug Project – Wk4

by: Peter A.

It’s been a really productive week, not to mention an extra day (Tuesday), which held the prospect that we might actually get some painting done – and we did!

The prototype tiller wheel handles were presented on Monday and most lovely they are. These together with the refurbished metalwork will deliver us a tiller wheel like no other! Wait and see….

In preparation for some painting, with considerable racket echoing around the yard as the needle gun persuaded the old deck paint to part company with the steel, There is still a bit more to do around the stern area.

The staging off the front of the boat is in preparation for assessments with respect to the handling of the winch cables to the mud hopper bollards. The front end of a hopper will be simulated for these developments.

With Tuesday being the only day left this year providing the conditions in which we could get some paint on, we made the effort to dry the boat off and let the sun warm the structure. By the afternoon, the first coat of red oxide was being applied to the cabin. We also managed to complete the first coat of hull blacking, which had remained unfinished.

The rudder bottom bearing was well worn, with about 3mm of ovality in the joint. The decision was taken to cut the skeg off and re-fettle it. To this end, the socket has been re-bored to round and the pin re-profiled too. A sleeve will then be inserted to provide us with a rattle free rudder bearing.

Our chippies have also been aboard attending to the woodwork on the cabin doors and also cleaning down the dash board to get it to a state where it could be varnished. As received, It was just grubby and well worn.

The weed hatch assembly has had a makeover. Having needle gunned it to reveal just how much metal remained, a new thrust plate was welded on and the whole assembly blacked. The threads of the two lock screws that clamp it in place were completely worn and did not grip, so that function has been renovated with new parts.

Now, the engine. With the new gaskets on hand, the two heads were were refitted and the necessary valve clearance adjustments made. This was followed by the replacement of the three manifolds and the extraneous plumbing for fuel and water. After a full check for the tightness of all the nuts, bolts and glands, it was time to crank the engine.

The batteries had been on charge for a couple of days, so with the decompression levers lifted, we proceeded to prime the fuel system first, before dropping the levers and going for engine start. Pleasingly, it started straight away and ran with no signs of any leaks – result! Oh, I should have mentioned that we did put some new oil in first!

When we purchased this tug, it arrived with a free gift stored down in the bilge under the cabin floor. Since now is the correct seasonal time to deploy it, the deed was done.

Finding suitable painting days at this time of year is a tad tricky, but that is what we need to get most of the remaining work done. So, if global warming could oblige at the start of ’23, that would be most appreciated.

Season’s greetings to the team – well done, great progress so far.