Western Depot this week

Maintenance

Western Depot this week

by: Steve P.

This week saw more significant changes at Western depot with containers arriving and departing, and the barn’s new steel framework starting to take shape. While the fabrication team continued to weld the new steels for the barn Steve P and Bob A’s teams worked to remove more of the old barn roof so that the new steels can be fitted. The roof trusses proved heavier than expected but with judicial use of the scaffold tower and ropes these were safely removed and lowered to the ground leaving yet more material for John D’s team to move over the Prentice’s field.

Reg decided that yet more trenches had to be dug to provide power to the new containers, but by the end of Monday these had been completed and the yard was the clearest ever, ready for the arrival of the new toilet block and office containers on Tuesday. By the time the teams came back in on Wednesday Reg and Martin had installed the 2 new containers and the toilet block was plumbed in and ready to go.

While the old office container was being emptied ready for its move Jeff decided to do a trial fit on the lintel for the right-hand side of the updated barn, and after significant efforts this was positioned and pulled into place at which point everyone decided that this wasn’t a trial, and that the beam could stay there!

Mid-morning the container lorry arrived with a new storage container that will be used to store equipment while the existing containers are reconfigured, and the crane on the lorry made short work of placing this in the recently cleared yard. The crane then lifted out the old office container, but with some excitement as the water pipe was broken for a second time, but this was soon repaired and the container moved to Prentice’s field.

These moves were further complicated by the roadworks outside the depot, with the temporary traffic lights being set to red in both directions so that the lorry could pull out and then reverse through the roadworks and into Prentice’s field, but all the moves were completed relatively quickly.

Attention then turned to moving the septic tank that was sited below the office container but the forklift came in handy to loosen this from its foundations and allow another lift by the lorry, with the tank and container being re-sited in their new temporary home on footings prepared by John D and his team. The only problem that this left was a large hole where the tank had been, and no water connection to the hospitality unit, but a team effort soon saw the hole partially refilled with rubble and a temporary water connection made.

With the steel lintel in place work on the barn started to focus on getting the roller shutter door in place while we still had clear access for the forklift as the door at 3m wide and 3.5m high is significantly heavy. After measuring and remeasuring the door uprights were positioned and partially bolted in place; the current plan following some YouTube video analysis by Reg and Martin is to position and secure the roller door drum into position and then secure the slats, but this will have to wait for the end of lockdown.

The end of the day saw another conger line procession around the yard carrying the first 10m long steel roof beam that Mike had fabricated, but it was too late in the day to lift this into position so Andy P took the opportunity to paint it with red oxide while it was at ground level rather than 3+ metres in the air. Overall, we now have a significantly different looking WD compound with the new containers in place and what somewhat thought looked like Sarcen stones and lintel for the barn – the Stonehenge (Ironhenge?) of Eastington!