Westfield (John Robinson) Lock progress

Phase 1B
Restoration

Westfield (John Robinson) Lock progress

by: Jon P.

Since the last report at the end of November, we’ve had a further 3 visits from WRG – one from London WRG and two from Kent & East Sussex Canal Restoration Group (KESCRG). The volume of earth coming out of the lock is sometimes hard to believe, so we’re extremely grateful for the fantastic support in terms of digger and dumpers from Plantforce. Unfortunately our temporary vehicular access agreement has lapsed, so we’re trying to negotiate an extension with Ecotricity. This has resulted in us being unable to use the supplied plant for the last weekend visit, which was very frustrating for all concerned – we had hoped to finish the clearance of the lock chamber. Luckily, the volunteers aren’t easily defeated and Martin had an alternative plan ….

Martin tries to clear the lock without a digger

By the time we’ve finished removing the spoil, it’s estimated we’ll have moved 650 cubic metres or 1150 Tonnes of soil / silt / clay. We’ve also found around 90% of the coping stones, including 3 of the 4 complicated hinge quoin stones. KESCRG have moved a large proportion of the coping stones away from the edge of the lock, sorting them by thickness and stacking them at the back of the site.

We’ve also cleared scrub from the proposed LH bend into the Missing Mile below Westfield Bridge, and also from the land acquired alongside the Oldbury Brook to permit the construction of a linking aqueduct. A sloping ramp has been constructed from the west down under Westfield Bridge – this is to allow plant access into the main lock chamber.

Clearing the LH bend along the fence
Clearing under the bridge

As the lock chamber becomes exposed, it’s encouraging to observe the relatively sound condition of the remaining lock walls The plan is to clear the invert of the lock completely, then erect scaffolding throughout the lock. This will allow access to the top of the walls, where we can remove the loose bricks and clean up the remaining brickwork. Then the rebuild can begin! It’s estimated that, on average, we’ll need to rebuild about 10 courses of new brickwork front to back of the walls (about 900mm thick). Then the coping stones and hinge quoin stones will need to be placed level. Other work on the lock chamber will involve cutting out and making good two new lock ladder recesses. The missing south-eastern upper gate recess, ground paddle hole, portion of the cill, and the wing wall will all be incorporated in the new aqueduct structure. This will also carry the new towpath route past the lock and towards the bridge.

Future activity includes several more weekend visits during 2023, together with 3 consecutive weeks of WRG Canal Camps in July. These will see up to 20 volunteers each week working on the lock and, eventually, the aqueduct.

For a link to a You Tube video about the Westfield (John Robinson) Lock restoration on Court above the Cut – take a look at https://youtu.be/yaXbg4UZpl8 – this includes aerial footage and, unfortunately, an interview with me. Another YouTube video, with the potential to reach 77 000 subscribers, is on Paul and Rebecca Whitewick’s site – here’s another link https://youtu.be/0kxQ5Zox4XQ