Weymoor Culvert Work Camp Week 1

Phase 2
Restoration

Weymoor Culvert Work Camp Week 1

by: Neil D.

The first of two, week long WRG work camps at Weymoor Bridge Latton began on 17th August. The purpose of these camps being the construction of a Culvert below the bridge to take a stream under the Canal. It would appear that the stream is new and wasn’t there when the Canal was originally constructed as no sign of any previous Culvert has been found. Most likely it is a result of all the Gravel extraction in the area and takes the run-off from these? The stream is at too low a level to flow into the Canal, hence the requirement for the Culvert. This first week’s camp consisted of a sizeable contingent of Duke of Edinburgh Award Scheme participants and the first task was to excavate a trench to take the two large diameter pipes that will form the Culvert.

Excavating the trench for the Culvert pipes

Prior to this the stream had been diverted (see previous blog) to enable the trench to be dug but, a large volume of water still seeped into the site due mainly to the porous ground on each side. Pumps were installed after the excavation to keep the site de-watered for placement of the pipes which had to be cut and joined on-site to give a length long enough to pass under the Canal and Towpath. The following day a significant problem showed itself. As the pumps could not be left running overnight the site filled with ground water and the following morning the pipes were found floating in it, there natural buoyancy and the trapped air in the strengthening ribs being the cause. The answer was to weight down the pipes with sand bags on top and lengths of steel reinforcing bar inside them.

The pipes in-situ with well head de-watering in progress

The next task was to build block facing around each end of the pipes and to cover them in a lean mix of Concrete Blinding. This was to make a sound base to construct the matrix of reinforcing bar over the pipes for a cast concrete slab. The rebar would also turn through 90 degrees at each side to reinforce the cast concrete side walls that would be added later.

The block facing at each end about to start
The weighted down pipes seen below the overnight ground water rise

The first week has been very busy and although slightly behind where we had hoped to be, good steady progress was made and week 2 should see the reinforcing go in and concrete slab cast. Fortunately, the weather at least has been kind to us.